Proposed new fast-track electricty connections system unveiled

Ofgem has today (February 14) announced its minded-to decision on the proposed Connections Reform process that would fast-track renewable energy projects if they can be operational quickly and are needed to hit the UK Government’s clean power targets for 2030.
The new system, which prioritises projects that are “ready” and “needed”, would see new, accelerated offers made by the end of the year, with the first connected and operational from 2026.
Stephen McKellar, Head of Grid and Networks at Scottish Renewables, said:
“As the connections queue has more than 700GW of projects waiting to connect - almost four times the electricity demand we will need by 2050 - we welcome Ofgem’s continued efforts to address this issue through reform.
“While these moves from Ofgem are welcome, it is vital for the future success of Scotland’s renewable energy industry that any decisions on moving or removing projects with grid connection agreements are based on sound, evidence-driven analysis to avoid unintended and potentially negative consequences.
“The need to urgently find a solution cannot be overstated and any reform must be implemented as quickly as possible so that we can get moving to build the projects our future clean energy system will need.”
Ends
Notes:
- Free to use image of Stephen McKellar.
- Ofgem’s press release: ‘Clean power by 2030 one step closer as proposed new, fast-track grid connections system is unveiled’.